2013 Road Maintenance Project (ENG-13-012) Work Schedule:rnrn9/16/15 WednesdayrnAsphalt Robert Roadrnrn9/17/15 ThursdayrnProof Roll Savoy rnClean & Prep Buxtonrnrn9/18/15 FridayrnAsphalt Buxton Roadrnrn9/21/15 MondayrnPremix Peter BourgeoisrnClean & Prep Savoyrnrn9/22/15 TuesdayrnSoil Cement Peter Bourgeoisrnrn9/23/15 Wednesday rnAsphalt Savoyrnrn9/24/15 ThursdayrnPremix Laurel Ridge Roadrnrn9/25/15 FridayrnSoil Cement Laurel Ridge Roadrnrn9/28/15 MondayrnPatching Bayou TerracernProof Roll Laurel Ridgernrn9/29/15 TuesdayrnAsphalt Peter Bourgeoisrnrn9/30/15 WednesdayrnAsphalt Laurel Ridgernrn10/1/15 ThursdayrnPatching Bayou Terracernrn10/2/15 ThursdayrnPatching Bayou Terrace